Ferrocarrils de la Generalitat Valenciana (FGV) hopes to have the upgraded Puerta del Mar TRAM stop operational in time for Alicante Bonfires 2027. The project, scheduled to begin towards the end of 2026, will extend the platform from approximately 33 to 75 metres and adapt the tracks for longer, higher-capacity trams. The investment amounts to around €3.26 million.
Key facts at a glance
- FGV plans to begin work at Puerta del Mar in late 2026.
- The platform will be extended from 33 to 75 metres.
- The overall project budget is approximately €3.26 million.
- The upgraded stop is intended to accommodate trams carrying more than 280 passengers.
- FGV is targeting June 2027, but completion before the Bonfires is not guaranteed.
Puerta del Mar is one of the best-known stops on the TRAM d'Alacant network. Located close to Postiguet Beach and Alicante's seafront, it serves an area popular with both residents and visitors.
Its location makes the upgrade particularly relevant ahead of the Bonfires of Saint John, when thousands of people travel around Alicante to enjoy the festival's monuments, street celebrations and other events.
Will Puerta del Mar TRAM stop be ready for Alicante Bonfires 2027?
FGV aims to have Puerta del Mar operational for the June 2027 Bonfires celebrations, but a definitive completion date has not been confirmed.
The announced timetable anticipates construction beginning in late 2026, with an estimated execution period of eight months.
This means that reopening in time for the festival remains a target rather than a guaranteed outcome.
Important information for visitors
If you plan to use the TRAM during Alicante Bonfires 2027, check the latest service notices before travelling. Construction schedules and the availability of individual stops may change.
What work will be carried out at Puerta del Mar?
The project will extend the central platform and modify both tram tracks to accommodate longer vehicles.
The existing platform is approximately 33 metres long. The replacement is planned to measure 75 metres in length and 4.5 metres in width.
The work will also involve improvements to the surrounding area, coordinated with Alicante City Council.
Approximate length of the existing platform.
Planned length after the upgrade.
Construction and project supervision.
Expected construction period.
Why does Puerta del Mar need a longer platform?
The extension will allow the stop to accommodate the new Series 4500 trams, which are approximately 45 metres long and offer greater passenger capacity.
The existing Series 4200 trams measure around 32.3 metres. The newer vehicles require platforms and track layouts suited to their greater length.
FGV also plans to adjust the tracks to improve access for the longer trams.
| Feature | Current trams | New trams |
|---|---|---|
| Series | 4200 | 4500 |
| Length | 32.3 m | 45 m |
| Passenger capacity | 198 | 284 |
The difference represents 86 additional passenger places per tram, which could help transport more people on services operated with the new vehicles.
How much will the Puerta del Mar upgrade cost?
The total budget is €3,263,824. This includes construction work and project supervision.
The upgrade forms part of FGV's broader preparations to introduce newer, higher-capacity trams on the Alicante network.
Which TRAM line serves Puerta del Mar?
Puerta del Mar is served by Line 5 of the TRAM d'Alacant network and is located close to Postiguet Beach and the Paseo de Gómiz seafront promenade.
The stop provides access to one of Alicante's busiest visitor areas, particularly during the summer and major celebrations.
Construction may temporarily affect the stop and its surroundings. Any confirmed changes to services or routes should be checked through official TRAM announcements.
How could the project affect travel during Alicante Bonfires 2027?
If the works are completed and the stop reopens before the festival, Puerta del Mar will be able to accommodate larger trams during Alicante Bonfires 2027.
However, FGV has not guaranteed that the project will be finished by June.
- Check Line 5 services before travelling.
- Confirm which stops are operating if construction is still under way.
- Allow for possible service changes during busy festival periods.
- Follow official TRAM updates for schedules and travel information.
How many new trams are planned for Alicante?
FGV plans to allocate six new Series 4500 trams to the Alicante network as part of an order for 22 vehicles.
The new trams, manufactured by Stadler in Albuixech, are designed to offer greater capacity, improved accessibility and a more comfortable passenger experience.
Upgrading Puerta del Mar is one of the infrastructure changes needed to accommodate these longer vehicles.
Puerta del Mar prepares for a major transformation ahead of Bonfires 2027
The Puerta del Mar project will modernise an important part of Alicante's tram network, allowing longer vehicles with increased passenger capacity to use the stop.
FGV hopes to have the work completed in time for Alicante Bonfires 2027, although the final timetable will depend on the progress of construction.